Phases

The four major phases to the Foster Hospital renovation project are outline below, with the corresponding time frames:


ERPhase 1: May 4 – August 20, 2015

  • Level 1 Office Suite
  • Accounting Office
  • Rounds Room


Phase 2: August 14 – October 7, 2015

  • ECC
  • Nuclear Medicine Support
  • Radiology Reading
  • Individual Offices


Phase 3: September 30 – March 2, 2016

  • Waiting Room
  • Internal Medicine Treatment
  • Ultrasound 2
  • Radiology Floor
  • Northern Exam Rooms
  • Individual Office
  • Pharmacy
  • Isolation
  • Restrooms
  • Conference Room
  • Level 2 Office Suite
  • ECC Rounds Room


New Waiting Room RenderPhase 4: March 3 – July 22, 2016

  • Service Alcove
  • Internal Medicine Rounds Room
  • Southern Exam Rooms
  • Dermatology Treatment
  • Ophthalmology Treatment
  • Ultrasound 1
  • Echo
  • Cardiology Exam
  • Neurology Treatment